Major improvement work for the West Coast Main Line at Watford

Major improvement work on the West Coast Main Line at Watford will get underway in 2014 to improve the punctuality of train services on Britain’s busiest mixed-use railway line.

The £81m improvement scheme begins in May 2014 and continues over 16 days between 9-25 August 2014. Further work is also scheduled to take place over Christmas 2014 and in early 2015.

During the project, passenger trains will be unable to use a 12-mile section of the West Coast Main Line around Watford Junction station. Train operators will be making alternative arrangements to help passengers complete their journeys during the line closure.

Dyan Crowther, Network Rail route managing director, said: “This scheme represents significant investment in the southern end of the West Coast Main Line to improve punctuality and make the railway more reliable.

“This line has seen tremendous growth in traffic and passengers over the last five years with the section at Watford being one of the most intensively used, high-speed sections of track in the UK. This work is absolutely essential to maintain the punctuality that passengers and our freight customers rightly expect. “

Usually, Network Rail would have carried out work of this kind over a number of weekends, requiring train services to be replaced repeatedly by alternative transport. The work at Watford would have required 54 complete weekend closures of the line, disrupting passengers for well over a year. By carrying out the work in five longer closures, engineers expect to be able to install the new signalling, replace track and junctions earlier and avoid disrupting rail travel plans for a large number of weekends throughout 2014 and 2015.

Dyan Crowther continued: “There is never a good time to carry out major work on such a busy route. However, after careful discussion with the train operators and industry partners, it became apparent that carrying out this vital investment over five longer closures between May 2014 and Easter 2015 when fewer people travel would, overall, cause less disruption.”

During the project, the signalling at Watford will be upgraded alongside new junctions and track to provide more flexibility for train services and better reliability.

To enable the work to be completed, trains will be unable to run on the West Coast Main Line through Watford on the following dates from May 2014:

3-5 May 2014

8-25 August 2014

25-29 December 2014

14-22 February 2015

3-6 April 2015

Chris Gibb, chief operating officer for Virgin Trains, said: “We shall ensure that all customers have a reliable way of travelling to and from London principally by being able to use other train operators’ services but in some cases by taking a replacement coach service for a short portion of the journey. We are starting a dialogue now with industry partners that puts the customer first, but at the same time allows Network Rail to carry out this essential work.”

Patrick Verwer, London Midland managing director, added: “We want our customers to have good journeys with minimum disruption. This is much needed investment and a series of closures is the quickest way of bringing the benefits of this major upgrade to our passengers. It gives certainty and allows us to plan good quality alternative travel arrangements. We are now working closely with Network Rail and other industry partners to ensure that there is a comprehensive programme of communication with good passenger information available well ahead of and during the closures. It’s vital that passengers are aware of what’s going on so they can plan their journeys and allow enough time to get to their destinations.”

The work at Watford is in addition to the £40m of investment announced by Network Rail last month to improve performance on the southern end of the West Coast Main Line through a programme of work aimed at tackling the most common cause of delay.

Alongside this project, Network Rail intends to increase the line speed of the fast lines through Watford to 125mph, from the current 80mph, and is investigating the feasibility of this.

Notes to editors

The work in detail:

•  Three junctions will be renewed to the north, south and in Watford Junction station itself to improve the track layout and make it more reliable.

•  Over nine miles (15km) of track to renew

•  Upgrades to the overhead line equipment in the area to make it more reliable.

•  Renewing crossovers to facilitate future maintenance of the main line while keeping train services running.

•  The signalling along 12 miles of railway between Kings Langley – Watford Junction and Bushey will be completely renewed to improve reliability and provide more flexibility. This work includes 11 new gantries, 39 signal posts and approximately 120km of cabling.

•  The signalling power supply system will also be upgraded.

Dates of the West Coast Main Line closure at Watford Junction:

•  May 2014: 2330 Friday 2 May 2014 to 1030 Monday 5 May 2014 (bank holiday)

•  August 2014: 2230 Friday 8 August 2014 to 12noon Monday 25 August (bank holiday)

•  Christmas 2014: 2300 Wednesday 24 December through to 0400 Monday 29 December (the National Rail network is closed to passenger services on Christmas Day and Boxing Day)

•  February 2015: 0200 Saturday 14 February through to 0600 Monday 23 February

•  Easter 2015: 2230 Thursday 2 April to 0600 Tuesday 7 April

London Overground services between Watford Junction and London Euston will continue to run throughout the closure’s listed above.

Network Rail is in discussions with rail freight operators about expected demand and how rail freight traffic can be accommodated during the closures.


Related links

Topics

  • Art, Culture, Entertainment

Regions

  • England

Visit our Media Room website for the latest news, press releases and the company factsheet. To receive our content live, as and when we publish it, you can sign up to follow us. Go to Follow Virgin Trains and click on ‘Create account’.

Virgin Trains has revolutionised rail travel by creating a high speed, high frequency service that has cut journey times and made rail journeys more comfortable. It has operated the West Coast passenger train franchise since 1997, serving key UK cities including London, Birmingham, Manchester, Liverpool, Preston and Glasgow.

Virgin Trains is the brand name of Virgin Rail Group (VRG), which is owned 51 percent by Virgin Group and 49 percent by Stagecoach. The Department for Transport (DfT) has awarded VRG a franchise contract, which started on 9 December 2012 and will run for up to 23 months. The DfT announced on 26 March 2013 a programme for letting future franchises, with the long-term West Coast franchise expected to start in April 2017.

Virgin Trains has been recognised in numerous awards. In September 2012 Business Traveller magazine readers voted the company the Best UK Domestic Rail Operator for the sixth year running. In 2011 the company was named Best Rail Operator in the Group Leisure Awards (which it also won in 2009 and 2010). In 2011 Virgin Trains won the British Quality Foundation's Achievement Award for Customer Satisfaction.

Customers consistently rate the company the top long-distance rail franchise operator, as measured by the National Passenger Survey (NPS) run by industry watchdog Passenger Focus. In the most recent NPS (Spring 2013) overall satisfaction was 92%, equalling our best ever score from the previous survey (Autumn 2012).

Virgin Trains first achieved Investors In People accreditation in 2007 and this was renewed in 2010; the IIP Gold award was achieved in 2011. In May 2013 Virgin Trains renewed it accreditation against the criteria of the European Foundation for Quality Management's (EFQM) Excellence Model, which it originally achieved in May 2011 The company’s Learning and Development team won a National Training Awards 2011 West Midlands award for its Coaching Culture programme.

For more information about Virgin Trains visit the Virgin Trains' website  or the Media Room website

Contacts

Virgin Trains Press Office

Press contact 0845 000 3333