Press release —

Halfway to doubling our size – and right on track

(Gardermoen, 27 February 2014) After breaking ground in 2011, construction of the new departures and arrivals hall, new railway station and new pier has reached the halfway mark. When the expansion project is completed in April 2017, the capacity of Oslo Airport will rise to 28 million passengers, compared with the current 23 million.

“The opening date is now set for 27 April 2017,” says Nic. Nilsen, managing director of Oslo Airport.

Simultaneous operation and expansion
It has been a premise ever since the beginning that the expansion project must not pose an obstacle to air travel.  In the midst of all the construction, which is one of Norway’s largest land-based development projects, OSL has repeatedly been named Europe's most punctual airport.

“Our challenge is to build and operate simultaneously in the same place, and do it successfully. We are very pleased that we are now halfway and have managed to maintain good punctuality, even in winter,” says Nilsen.

In January, 750 people were working at the construction site, and the project is far below the industry average in terms of lost time injuries.

“Safety is our highest priority. After three years of construction work, we have not had any serious incidents and I’m happy to say the number of lost time injuries is minimal,” says Nilsen.

Travel will proceed as normal 
When the expansion is completed, there will be short walking distances from the new pier, which will provide easy access to public transport and offer many exciting shopping and dining options.

“We have chosen a passenger-friendly solution:  We are expanding the existing terminal to boost capacity and we have focused on keeping the concept of a compact airport with short distances,” says Nilsen, adding that this will also apply to passengers during the construction period.

“It requires a lot of planning and coordination, and we take pride in doing everything we can to ensure that the expansion project will not affect passengers, and that travel will proceed as normal.

More temporary solutions
A number of compensating measures are necessary to prevent the expansion project from disrupting travel.

Several gates have been closed to connect the new pier to the existing terminal. One of the consequences of this is that there will be more transport by shuttle bus during the expansion period. In August 2012, a temporary domestic pier was also opened at the request of passengers and airlines, to avoid using shuttle buses to and from domestic aircraft.

Predictability for everyone
Open and precise communication about the expansion project has been crucial, and will continue to be of great importance in the years leading up to the opening.

“We aim to be honest and open with passengers and those who work at the airport. Around 15,000 people employed by 150 companies work at OSL. We are doing everything we can to promise a certain amount of predictability for all,” says Nilsen.

Climate-friendly steps
Oslo Airport's goal is to be as environmentally friendly as an airport can be. A number of steps have consequently been taken to shrink the airport’s carbon footprint.

“Among other things, the roof of the new pier is wood, not steel. Oslo Airport is one of the first in the world to use snow for cooling and waste for heating,” says Nilsen.

“One confirmation that we are on the right track is that the new departures and arrivals hall and the new pier will be certified as 'Excellent' in the BREEAM Bespoke rating system. BREEAM is the world’s foremost environmental assessment method for buildings, and the choice of a wooden roof on the new pier together with sound energy solutions utilising sewage and snow are key elements here.”

In addition, the railway station is being expanded to facilitate an ambitious public transport target of 70%. As of 2013, 65% used public transport for travel to and from the airport.

See video of how the new Oslo Airport will look here: Oslo Lufthavn i 2017 (Youtube - text in Norwegian)

Related images and illustrations attached below.

Topics

  • Art, Culture, Entertainment
  • Media, Communication
  • Transport
  • Vacation
  • Travels
  • Public sector
  • Air service
  • Freight, Transport
  • Adventures

Categories

  • airport development

Oslo Lufthavn AS (OSL) owns and operates Norway's main airport, Oslo Airport at Gardermoen. OSL is an important transport hub in Norway with 23 million passengers and more than 230,000 aircraft movements every year. Oslo Lufthavn AS is a wholly owned subsidiary of Avinor.

Contacts

Related content

  • Oslo Airport celebrates its 15th anniversary

    Tuesday, 8 October marks the 15th anniversary since Oslo Airport (OSL) opened its doors and runways as Norway’s new main airport at a ceremony presided over by His Royal Majesty King Harald on 8 October 1998.

  • Busiest in Scandinavia in November

    With 1 811 117 passengers, Oslo Airport was the busiest airport in Scandinavia in November. Passenger volume was up 1.3% compared with November 2012.

  • New record year for Oslo Airport

    In 2013, just under 23 million passengers travelled via Oslo Airport. This is 4.0 per cent or roughly 876,000 more than in 2012 and is the highest number of passengers ever to travel through Oslo Airport.

  • New CEO takes charge

    Øyvind Hasaas took over as the new CEO of Oslo Airport Monday.

  • Traffic takes off during summer holiday

    Despite the gorgeous summer in Norway, international traffic rose by 2.5 per cent in July compared with July last year. Domestic traffic was up by 1.7 per cent.

  • New roof takes shape

    The expansion of Oslo Airport reaches a new milestone this week when the first laminated wooden beams for the new departures and arrivals hall in the west central building are hoisted into place.

  • New year off to a flying start

    The start of 2014 has been characterised by more passengers travelling longer distances. In January, 1 632 823 passengers travelled through Oslo Airport and international flights increased significantly compared with the same month last year.

  • Oslo Airport uncovers violations

    The development organization at Oslo Airport, which is responsible for the major expansion project at the airport, has uncovered cases of adverse working conditions at a subcontractor.

  • Update: No strike at Oslo Airport

    The possible strike by refueling personnel and airport fuel suppliers at Oslo Airport is called off. Airtraffic goes as planned.

  • Oslo Airport receives prestigious environment award

    On Tuesday last week, Oslo Airport was awarded ACI’s ECO Innovation Award. Awarded for the tenth time this year, this is the first time Oslo Airport has won the prize. "The justification for giving us the award is our systematic and comprehensive work on environment issues, and of course we are elated," says Managing Director Nic. Nilsen.

  • Thieves beware!

    In cooperation with the police, Oslo Airport will step up efforts this summer to make the airport a safe place for all travellers.