Better future journeys through Staffordshire after £12.5m upgrades
Rail journeys on the West Coast Main Line through Staffordshire have been improved thanks to major railway upgrades this August.
Network Rail has invested £12.5m renewing tracks, points, bridges and viaducts over the last three weeks.
The work took place during a rare 21-day closure of a 50-mile stretch of the route from Stone through Stoke-on-Trent to Stockport where a major £20m bridge project was carried out.
With no train traffic on the tracks, hundreds of railway workers from Network Rail and its supply chain were able to complete the essential infrastructure upgrades, including:
- Refurbishment of the River Trent Viaduct - structural and waterproofing improvements, including new concrete slabs and upgraded drainage
- Track renewal at Stone station - 22 track panels replaced, 2,500 tonnes of ballast refreshed, and over 50 new rails installed
- Level crossing upgrades - Meaford, Church Lane, and Aston-by-Stone crossings were upgraded to improve safety and infrastructure resilience
- Longport station footbridge – ongoing improvements to staircases, concrete work and repainting
- 500m of track and drainage improvements near Trentham
- 250m of track upgrades near Hixon
This video shows the tracks at Stone during the railway closure:
Those projects were carried out between 2 and 22 August with trains running on the line again on Saturday 23 August.
Steve Hopkinson, Network Rail’s West Coast South route operations director, said: “I would like to thank passengers and local people for their patience while we carried out this major programme of investment in Staffordshire. Our upgrades will help to future proof this important rail corridor, improve safety and help us to deliver better journeys.”
Jonny Wiseman, customer experience director at London Northwestern Railway, said: “We are pleased that the Potteries line has now returned to a normal timetable following a suite of important improvements. I would like to thank our passengers for their patience while Network Rail carried out these works.”
Meanwhile over the recent August bank holiday, the West Coast Main Line south also saw improvements delivered.
Workers installed 300 metres of new drainage just north of Leighton Buzzard station.
As this section of railway has been prone to flooding during heavy downpours, the new drainage aims to reduce that risk and keep trains moving during bad weather.
Passengers are reminded they can plan their journeys in advance by visiting www.nationalrail.co.uk.
To find out how Network Rail maintains and improves the railway you can visit: https://www.networkrail.co.uk/running-the-railway/looking-after-the-railway/
Topics
Categories
Regions
About London Northwestern & West Midlands Railways
For further information on this release, email press.office@wmtrains.co.uk
London Northwestern & West Midlands Railways operates both West Midlands Railway and London Northwestern Railway services.
- London Northwestern Railway services operate between Liverpool and Birmingham, and on the West Coast Main Line to and from London Euston.
- West Midlands Railway services operate to destinations across the West Midlands via Birmingham New Street and Birmingham Snow Hill.
For more information on these services visit westmidlandsrailway.co.uk or londonnorthwesternrailway.co.uk
If you have been sent this press release, this is because we believe this to be of interest to you.
To sign up for all future releases, visit our newsroom and subscribe to our updates. You can unsubscribe to our releases at any time.