News —
Bad Lauchstädt Energy Park Produces Green Hydrogen For the First Time
Green hydrogen has been produced for the first time in the 30-megawatt electrolysis plant at the Bad Lauchstädt Energy Park. The electrolysis plant, jointly operated by Uniper and VNG, is the heart of the hydrogen production process: it uses renewable electricity from the connected wind farm to split water into hydrogen and oxygen.
The next step involves optimizing the interaction of electricity generation, electrolysis, gas processing, and transport under real-world conditions and coordinating the technical processes. With this initial hydrogen production, not only has an important technical milestone been reached, but the overall project is also moving closer to its goal of providing green hydrogen on an industrial scale. The completion of the integrated hydrogen system is planned for 2027.
Konstantin von Oldenburg, Managing Director of VNG Handel & Vertrieb, said at the commissioning of the electrolyzer: “With the production of the first hydrogen, we are getting closer to our shared goal of converting renewable energy into an industrially usable energy carrier. The first hydrogen molecules are a harbinger of the approximately 3,000 tons of hydrogen that our anchor customer will purchase and use industrially next year. The test operation now commencing is an important step in integrating the individual components and paving the way for future deliveries,” said von Oldenburg.